We’re improving the water supply network between High Hurstwood and Burnt Oak
We’re improving the water supply network between High Hurstwood and Burnt Oak
26/01/2026
Message from South East Water:
The water pipes in Burnt Oak Road, Uckfield, have a history of frequent bursts, which has meant low water pressure and sometimes no water for our customers.
We’re sorry this happened; it’s not acceptable. We’re always working to reduce the number of leaks and bursts we have. With this in mind, to make the water supply in this area more reliable, we’re going to replace around 765 metres of pipeline.
What’s going to happen and when?
We’re going to replace around 765 metres of water pipes in Burnt Oak Road,
Uckfield.
We’ll be starting work on Monday 2 March. We expect
the work to take approximately 14 weeks. We’ll do our best to get the work done
faster if we can.
How will this affect
residents and businesses?
We’re sorry for the
disruption this work is going to cause; we know it’s inconvenient. We’ll do our
absolute best to keep it to a minimum.
For the safety of the
public and our team, we’ll need to close a section of Burnt Oak Road, covering
the main bend in the road, between the villages of High Hurstwood and Burnt
Oak.
We know road closures can
be disruptive and they are a last resort, however safety is at the forefront of
our minds. Diversion routes, agreed with East Sussex Highways, will be
signposted for the duration and published on our website.
Accessing property
We’ll maintain access for residents and businesses throughout the works, and
our customer liaison manager will be visiting those impacted to help understand
how we can minimise disruption while we complete this vital work.
While we will maintain access, there may be times when there may be a wait if
we’re working directly outside the entrance to their property or while we
finish a task, such as a concrete pour. The length of this wait will depend on
the task; it could be we just need to make the area safe to get by or it could
be that we need to finish that particular part of work.
The direction residents enter their property from may not be their usual route
or it may change as we move along the road.
Diversion routes, agreed by East Sussex Highways, will be available to view at southeastwater.co.uk/Burnt-Oak-Road and
will be signposted for the duration of the work.
Water supply
We may need to turn the water supply off for a short time when we connect our
new pipes to the existing network. We’ll let residents know at least 48 hours
beforehand, so they can plan ahead.
Need extra support?
If you know of any residents in your area who may need any extra support during
the work, please signpost them to our Priority Services Register. We have all
sorts of services to help customers who may need it. For example, if they’re
struggling financially, have an illness or disability or are looking after a
child under five.
They can find out more and sign up at southeastwater.co.uk/psr
Want to know more?
We’ll be regularly posting news and other
information at: southeastwater.co.uk/Burnt-Oak-Road
Thank you for your understanding while we improve the water supply for you and
your community.